Organization Name:
(组织名称) CHINA NUCLEAR POWER OPERATION TECHNOLOGY CORPORATION LTD.
(组织名称) CHINA NUCLEAR POWER OPERATION TECHNOLOGY CORPORATION LTD.
Organizational Unit:
(组织单位) Simulation and Engineering Center (abbr. SEC)
(组织单位) Simulation and Engineering Center (abbr. SEC)
Maturity Level:
(成熟度) Maturity Level 3
(成熟度) Maturity Level 3
Appraisal End Date:
(评估结束日期) Jun 30, 2016
(评估结束日期) Jun 30, 2016
Lead Appraiser:
(主任评估师) Chao-Pin Lee
(主任评估师) Chao-Pin Lee
Sponsor:
(发起人) Fuchang Shan
(发起人) Fuchang Shan
- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: All projects are located in Wuhan.)
Customer (Not Relevant: All customers are nuclear power plants. Customers does not affect the way processes are executed.)
Size: Projects are generally divided into large and small size. Size may affect engineering processes.
Organizational Structure (Not Relevant: All projects placement within Simulation and Engineering Center.)
Type of Work (Not Relevant: All projects are new development work.)Sampling Factor Values: Large (Size): Effort > 40 Person Months.
Small (Size): Effort <= 40=”” person=””>Subgroups: Large Projects: Large size projects.
30 People, 3 Basic Units
– Large
Small Projects: Small size projects.
24 People, 3 Basic Units
– Small