ITCEN SYSTEMS-2014-CMMI3

CMMI认证查询 cmmirz 10年前 (2014-01-22) 507次浏览 0个评论
Organization Name:
(组织名称)
ITCEN SYSTEMS
Organizational Unit:
(组织单位)
SI Division
Maturity Level:
(成熟度)
Maturity Level 3
Appraisal End Date:
(评估结束日期)
Jan 23, 2014
Lead Appraiser:
(主任评估师)
SeongUck Richard Nam
Sponsor:
(发起人)
Jeonghyo Seo
Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: All project in-scope is performed at the same location, SI Division in Seoul Korea. All work is performed at the same location, so this is not relevant sampling factor.)
Customer (Not Relevant: This organization has different customers, but it doesn’t impact to the application of processes and those processes are consistent across different customers. Regardless of customers, processes used are same and consistent across this organization.)
Size: Projects in this organization are categorized in the sizes based on complexity and effort involved. Quality assurance team and Project Managers apply a different set of processes for project depending on the size of a project. Processes could be different according to the size.
Organizational Structure (Not Relevant: Organizational structure does not impact to way processes are applied by the project. All projects are managed by senior manager and Quality Assurance team of Development Division.)
Type of Work (Not Relevant: All projects are kinds of information system software development. Their technical set is web based software development. The type of work doesn’t impact to the application of processes.)
Sampling Factor Values: Large (Size): Projects in this organization are categorized in the following sizes based on complexity and effort involved: • Large size > 10 people
Medium (Size): Projects in this organization are categorized in the following sizes based on complexity and effort involved: • 5 < medium=”” size=””>< 10=””>
Small (Size): Projects in this organization are categorized in the following sizes based on complexity and effort involved: • Small size =< 5=””>
Subgroups: Large Pjt: Projects in this organization are categorized in the following sizes based on complexity and effort involved: Large size > 10 people
24 People, 2 Basic Units
– Large
Medium Pjt: Projects in this organization are categorized in the following sizes based on complexity and effort involved: 5 < medium=”” size=””>< 10=””>
14 People, 2 Basic Units
– Medium
Small Pjt: Projects in this organization are categorized in the following sizes based on complexity and effort involved: Small size =< 5=””>
4 People, 1 Basic Units
– Small