CMMI认证

Siemens AG-2015-CMMI2

Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: Two locations (Erlangen, Bad Neustadt) working closely together according to same process on all projects, no difference in working. Other locations are not in scope.)
Customer (Not Relevant: External OEM car manufacturers for large production volumes with similar products (motor and inverter) only.)
Size (Not Relevant: All project sizes work according to the same process.)
Organizational Structure (Not Relevant: No difference due to common process, only one business unit.)
Type of Work: Customer projects and maintenance projects
Sampling Factor Values: Customer projects (Type of Work): Development of new systems
Maintenance projects (Type of Work): Maintenance projects for existing systems
Subgroups: Customer Projects with Large Scale Manufacturing Volumes: There are 5 projects in the OU, and there are yet no maintenance projects, this subgroup is the only one in the organizational unit
185 People, 5 Basic Units
– Customer projects