Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: All 3 projects are in Hefei with no process difference with respect to location.)
Customer (Not Relevant: Although there are two types of customer (government agency, internal customer), there is no process difference between different types of customer.)
Size (Not Relevant: All basic units are the same size with no differences in process execution.)
Organizational Structure (Not Relevant: All Projects are in the same department (R&D Center) with no process difference.)
Type of Work: There are 2 types of work: New Development and Feature Enhancement. Feature Enhancement projects are executed on the basis of existing system while New Development is not. This creates process differences in Requirement Development, System Design and Component Reuse, Product Integration and testing.
Sampling Factor Values: New Development (Type of Work): New Development with no existing products
Feature Enhancement (Type of Work): Development on the basis of existing product.
Subgroups: 1: Feature Enhancement projects which is built on existing product
14 People, 2 Basic Units
– Feature Enhancement
2: New Development projects which start from ground up
10 People, 1 Basic Units
– New Development