| Sampling Factors: |
Location (Not Relevant: All projects worked at same location. No impact on process execution.)
Customer (Not Relevant: Projects for similar customers, no impact on process execution.)
Size: Large, medium and small projects have minor differences in process execution.
Organizational Structure (Not Relevant: All projects worked in the same group. No impact on process execution.)
Type of Work: Some projects contract projects and others are internal R&D projects, with some process differences. |
| Sampling Factor Values: |
Large (Size): More than 40 man-months
Medium (Size): Between 10 and 40 man-months
Small (Size): Less than 10 man-months
Contract (Type of Work): Project work for External Customer contracts
Internal R&D (Type of Work): Project work for internal products |
| Subgroups: |
Medium R&D Projects: Internal R&D projects of Medium size
8 People, 2 Basic Units
– Medium
– Internal R&D
Medium Contract Projects: Contract projects of Medium size
8 People, 2 Basic Units
– Medium
– Contract
Large R&D Projects: R&D projects of Large size
10 People, 1 Basic Units
– Internal R&D
– Large |