| Sampling Factors: |
Location (Not Relevant: The 3 sites (Paris, Marne-la-Vallée, Poitiers) apply the same processes defined in ARPEGE asset library and have the same QA controls)
Customer (Not Relevant: Business customers in front of DIPRO projects and maintenances have no significant requirements regarding process to apply)
Size (Not Relevant: The OU focuses on large projects (global cost greater than 1 M€) and maintenances (TOP 30))
Organizational Structure (Not Relevant: All entities of the OU use the same processes defined in ARPEGE asset library)
Type of Work: There are 2 types of activities in the OU: development projects and maintenance activities
Agile or not: Projects and maintenances could use Agile technics or not |
| Sampling Factor Values: |
Project (Type of Work): Software development project (main evolution of an application).
Maintenance (Type of Work): Software maintenance activities (small evolutions and corrections of an application)
Agile (Agile or not): Project or maintenance using agile method / technics and cycle
Standard (Agile or not): Project or maintenance using standard method and cycle |
| Subgroups: |
Agile projects: Projects in Agile mode
24 People, 5 Basic Units
– Project
– Agile
Standard projects: Projects in standard mode
13 People, 5 Basic Units
– Standard
– Project
Standard maintenances: Maintenance activities in standard mode
87 People, 20 Basic Units
– Maintenance
– Standard
Agile maintenances: Maintenance activities in Agile mode
27 People, 6 Basic Units
– Agile
– Maintenance |