| Sampling Factors: |
Location (Not Relevant: All projects are working in the same location (and building), so this is not a relevant sampling factor)
Customer (Not Relevant: All projects are for similar customers.)
Size (Not Relevant: All projects are not significantly different in size, so this is not a relevant sampling factor)
Organizational Structure (Not Relevant: All projects are working under the same organization and management structure, so organizational structure is not a relevant sampling factor)
Type of Work: There are two types of work within the organisation 1.New Development 2. Maintenance |
| Sampling Factor Values: |
1. New Developement (Type of Work): A project newly developed by the development department
2. Maintenance (Type of Work): An existing project developed to upgrade and optimize based on the customer feedback and new requirement |
| Subgroups: |
1.: A project newly developed by the development department
17 People, 2 Basic Units
– 1. New Developement
2.: An existing project developed to upgrade and optimize based on the customer feedback and new requirement
15 People, 2 Basic Units
– 2. Maintenance |