| Sampling Factors: |
Location (Not Relevant: There is only one location, which is Beijing)
Customer (Not Relevant: There is no process distinction among the customers.)
Size: The projects are categorized as big and small
Organizational Structure (Not Relevant: Projects in team I & II are part of Software Division, they share same management team)
Type of Work (Not Relevant: All projects are MIS (management information system) related application development) |
| Sampling Factor Values: |
BG (Size): The effort used in development of the project is more than 100 staff months.
SM (Size): The effort used in development of the project is no more than 100 staff months. |
| Subgroups: |
Team I: The total effort used in development are more than 100 staff months
9 People, 1 Basic Units
– BG
Team II: The total effort used in development are no more than 100 staff months
28 People, 5 Basic Units
– SM |