| Sampling Factors: |
Location (Not Relevant: All team members are located in Chengdu, thus location is not relevant.)
Customer (Not Relevant: The OU develops new releases for an existing product, thus customer is not relevant.)
Size (Not Relevant: Since time-boxed (two weeks) sprint is used and team size is also fixed, size for each sprint is about the same. Thus size is not relevant.)
Organizational Structure: The OU has two development teams for different functions” enhancement.
Type of Work (Not Relevant: Only product”s new releases are involved, thus type of work is not relevant.) |
| Sampling Factor Values: |
T1 (Organizational Structure): Team 1 is responsible for developing content management features.
T2 (Organizational Structure): Team 2 is responsible for developing broadcast management features. |
| Subgroups: |
T1: The subgroup covers Team 1″s work.
22 People, 1 Basic Units
– T1
T2: This subgroup covers Team 2″s work.
10 People, 1 Basic Units
– T2 |