- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: Development projects are all in Beijing, it doesn’t affect the development process.) Customer (Not Relevant: All the products developed for the enterprises. It doesn’t affect the development process.)
Size (Not Relevant: Size are similar and it doesn’t affect the development process.)
Organizational Structure (Not Relevant: Organizational structures are same in all of the projects and all of the projects are in same organization.)
Type of Work (Not Relevant: All the projects are information system development)
Technology: There are two types of technologies: Asp.net and Java. The process of these two types of projects are different.
Sampling Factor Values: Asp.net (Technology): Projects using Asp.net technical platform Java (Technology): Projects using Jave technical platform
Subgroups: G1: Projects using Asp.net technical platform
15 People, 3 Basic Units
– Asp.netG2: Projects using Java technical platform
9 People, 2 Basic Units
– Java