| Sampling Factors: |
Location (Not Relevant: All development projects follow the standard processes. None process is location specific so location has no big impact on process implementation.)
Customer (Not Relevant: Technology driven approach, product based development follow the standard processes. No process is customer specific so customer has no big impact on process implementation.)
Size (Not Relevant: Product are developed on previous version product, new features are gradually added to product base. No process is categorized and implemented by size, so size has no big impact on process implementation.)
Organizational Structure (Not Relevant: All under same organizational structure. Organizational structure has no big impact on process implementation.)
Type of Work (Not Relevant: All product development projects following the same development process.)
Product Line: Standard development processes are tailored to fit differenct product line contexts. |
| Sampling Factor Values: |
ETC (Product Line): Electronic Toll Collection related vehicle, roadside, issue products.
WIM (Product Line): Weight charge and overrun detection products.
LiDAR (Product Line): Laser detection products for vehicle, traffic, and hub size, etc. |
| Subgroups: |
PJ-ETC: ETC product development projects.
88 People, 3 Basic Units
– ETC
PJ-WIM: WIM project development projects.
54 People, 3 Basic Units
– WIM
PJ-LiDAR: Laser detection product development projects.
32 People, 3 Basic Units
– LiDAR |