- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: Software development activities (appraisal scope) are carried out from a single location) Customer (Not Relevant: The processes are independent of the nature of the customers)
Size: The size of the project affects the way the processes are applied. Projects are divided into Small and Big according to the volume of Function Points estimation
Organizational Structure (Not Relevant: Software development activities and processes are the same for all areas of the organization)
Type of Work (Not Relevant: The organization only carries out software development projects/products)
Sampling Factor Values: Small (Size): Software Development Projects with estimation Big (Size): Software Development Projects with estimation >= 500 Function Points
Subgroups: G1: Software Development Projects with estimation
12 People, 2 Basic Units
– SmallG2: Software Development Projects with estimation ? 500 Function Points
13 People, 2 Basic Units
– Big