| Sampling Factors: |
Location (Not Relevant: same workplace)
Customer (Not Relevant: The same customer,- water resource government officials)
Size: The process varies slightly – mostly for risk management (more than 20 people)
Organizational Structure (Not Relevant: all projects are organized same way)
Type of Work (Not Relevant: all projects are in the same way regardless of work) |
| Sampling Factor Values: |
greater than 20 people (Size): Projects with more than 20 people
fewer than 20 people (Size): Projects with fewer than 20 people |
| Subgroups: |
small: projects run with fewer than 20 people
15 People, 1 Basic Units
– fewer than 20 people
big: projects run with more than 20 people
80 People, 4 Basic Units
– greater than 20 people |