- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: All projects are developed in a single centralized location in Chongqing.) Customer (Not Relevant: Customers does not affect the way of doing work.)
Size (Not Relevant: There is no specific classification of projects into Large Medium Small buckets. There’s no difference in doing work due to the project size.)
Organizational Structure (Not Relevant: All projects are developed following same processes.)
Type of Work: There are two types of work: waterfall development, or iteration development. The type of work may affect the engineering and management processes.
Sampling Factor Values: Waterfall Development (Type of Work): Projects that developed using waterfall lifecycle model. Iteration Development (Type of Work): Projects that developed using iteration lifecycle model.
Subgroups: Waterfall: Projects that use waterfall lifecycle model.
22 People, 2 Basic Units
– Waterfall DevelopmentIteration: Projects that use iteration lifecycle model.
14 People, 1 Basic Units