| Sampling Factors: |
Location (Not Relevant: Single location)
Customer (Not Relevant: All projects are required to follow the same process irrespective of the customer involved)
Size (Not Relevant: All projects are required to follow the same process irrespective of size)
Organizational Structure (Not Relevant: The OU consists of one group)
Type of Work: There are 2 types of lifecycles being followed – waterfall, iteration |
| Sampling Factor Values: |
Iteration (Type of Work): Iterative life cycle
Waterfall (Type of Work): Waterfall life cycle |
| Subgroups: |
Iteration: Iterative life cycle project
21 People, 2 Basic Units
– Iteration
Waterfall: Waterfall life cycle project
50 People, 5 Basic Units
– Waterfall |