| Sampling Factors: |
Location (Not Relevant: This factor is not applicable because there is no tailoring specific to the location that affects the implementation of the processes.)
Customer (Not Relevant: This factor does not apply because it does not involve tailoring affecting the implementation of the processes by customer type.)
Size: This factor is relevant. They have small and big ABAP projects based in the duration of the project. The tailoring guidelines are based on project size.
Organizational Structure (Not Relevant: This factor is not applicable because all projects belong to “Americas Regional Delivery Center (ARDC)”.)
Type of Work (Not Relevant: This factor is not relevant. They have only development project. There is no tailoring affecting the implementation of the processes by type of work.) |
| Sampling Factor Values: |
Small (Size): Duration between 1 to 3 months
Big (Size): Duration more than 3 months |
| Subgroups: |
Small Projects: ABAP development projects with duration between 1 and 3 months.
16 People, 1 Basic Units
– Small
Big Projects: ABAP development projects with duration bigger than 3 months.
79 People, 7 Basic Units
– Big |