| Sampling Factors: |
Location (Not Relevant: All projects in-scope is performed at the same location, R&D Center in Seoul Korea.)
Customer: This organization has two different customers, one is car electronics manufacturer and the other is OEM company. Projects in this organization are categorized in the following criterion based on complexity and effort involved. • Electronics parts company: DW • OEM: SS According to the type of customer, lots of tailoring options should be considered. Quality assurance manager and Project Manager apply a different set of processes for project depending on the type of item.
Size (Not Relevant: Most of projects relatively have similar size due to relatively similar productions, and it does not impact to way processes are applied by the project)
Organizational Structure (Not Relevant: Organizational structure does not impact to way processes are applied by the project. All projects are managed by senior manager and supported by Quality Assessment Team.)
Type of Work (Not Relevant: Projects in this organization have similar functions and features about AVN system. Regardless of type of work, processes used are same and consistent across this organization.) |
| Sampling Factor Values: |
OEM (Customer): This development approach based on “customer” represents relatively complex and long period development characteristics.
Electronic parts company (Customer): This development approach based on “customer” represents relatively simple and short period development characteristics. |
| Subgroups: |
SS: This development approach based on “customer” represents relatively complex and long period development characteristics.
31 People, 3 Basic Units
– OEM
DW: This development approach based on “customer” represents relatively simple and short period development characteristics. This type of development is due to a subcontract of OEM.
13 People, 1 Basic Units
– Electronic parts company |