- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: Only one location – Shanghai) Customer (Not Relevant: Customer of the organization is only China Post.)
Size (Not Relevant: Project size does not significantly influence process implementation in the OU and is not considered a management factor.)
Organizational Structure (Not Relevant: All projects are under the same department)
Type of Work: Productization project
Customization projectSampling Factor Values: Productization project (Type of Work): Productization project Customization project (Type of Work): Customization project
Subgroups: SG1: Productization project
30 People, 5 Basic Units
– Productization projectSG2: Customization project
22 People, 5 Basic Units
– Customization project