Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: Projects for government agency are usually located in customer site. This sampling factor has the same effect as Customer factor.)
Customer: There are two types of customers. Government and Industry customers.
Size (Not Relevant: As OU is a small sized organization, size of projects in this OU are usually small.)
Organizational Structure (Not Relevant: Functional team provide project team members.)
Type of Work (Not Relevant: Type of work of projects are similar and is not a tailoring option.)
Sampling Factor Values: Government (Customer): Projects for government agencies like military, law enforcement.
Industry (Customer): Project for civilian industry customers.
Subgroups: Government: Projects for government agencies.
14 People, 2 Basic Units
– Government
Industry: Projects for civilian industry customers.
8 People, 1 Basic Units
– Industry