| Sampling Factors: |
Location (Not Relevant: All projects use the same processes regardless of location)
Customer (Not Relevant: All projects use the same processes regardless of customer)
Size: Large projects (>1000 hours) are done slightly differently. However, this appraisal is scoped to only address large projects.
Organizational Structure (Not Relevant: All projects use the same organizational structure)
Type of Work (Not Relevant: All projects use the same processes regardless of type off work) |
| Sampling Factor Values: |
Large (Size): Project whose Actuals to date plus ETC total to >1000 hours
Small (Size): Project <1000 hours.=”” this=”” appraisal=”” was=”” scoped=”” to=”” include=”” data-ke-only=”” large=”” projects,=”” so=”” no=”” small=”” projects=”” were=””> |
| Subgroups: |
Fiserv CUS Large Software Development Projects: Fiserv CUS Large Software Development Projects
583 People, 27 Basic Units
– Large |