| Sampling Factors: |
Location (Not Relevant: No. Single site, therefore there are no subgroups. The same process used consistently.)
Customer (Not Relevant: No. Various customers, but the same process used)
Size: Yes. The size changes the process.
Organizational Structure (Not Relevant: No. Single company, no process related subgroups within the company)
Type of Work (Not Relevant: No. All development work projects, follow the same process) |
| Sampling Factor Values: |
Large projects (Size): more than 60 man month
Medium Projects (Size): 35- 60 man month
Small Projects (Size): Under 35- man month |
| Subgroups: |
Large projects: Projects over 60 man months
240 People, 14 Basic Units
– Large projects
Medium: Projects 35-60 man months
60 People, 7 Basic Units
– Medium Projects
Small Projects: Projects under 35 man months
40 People, 9 Basic Units
– Small Projects |