| Sampling Factors: |
Location (Not Relevant: Dongguan headquarters only sales department. R&D related departments are all in Wuhan)
Customer (Not Relevant: All customers are same category. The OU perform same types of work using same process set for all customers.)
Size: Projects of the OU are divided into 2 categories by size as a factor of project management. Small-size projects follow simplified processes according to the tailoring guidelines of the OSSP.
Organizational Structure (Not Relevant: R&D center for software development, system test group, quality assurance and configuration management)
Type of Work (Not Relevant: Product development) |
| Sampling Factor Values: |
Large Project (Size): Large (Project Effort > 30MM)
Small Project (Size): Small (Project Effort < =30=””> |
| Subgroups: |
SG1: Large Project
20 People, 3 Basic Units
– Large Project
SG2: Small Project
15 People, 4 Basic Units
– Small Project |