Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: Single location (Hangzhou))

Customer (Not Relevant: Customer is not a relevant factor because processes do not distinguish any tailoring depending on customer.)

Size (Not Relevant: The differences among project sizes are not affecting the tailoring.)

Organizational Structure (Not Relevant: All projects are within the Technical Research and Development Institute under the same management structure.)

Type of Work: Projects are generally divided into 4 types: which may affect project management, requirement development, design, integration and review processes. The 4 types are:
A1 – Embedded product platform project,
A2 – Embedded product improvement project,
B1 – Software system platform project,
B2 – Software system improvement project.

Sampling Factor Values: A1 – Embedded product platform project (Type of Work): Project involves embedded product and requires to develop a new embedded platform.

A2 – Embedded product improvement project (Type of Work): Project involves embedded product. And the development is based on an existing embedded platform.

B1 – Software system platform project (Type of Work): Project involves software system but no embedded product. And it requires to develop a new software platform.

B2 – Software system improvement project (Type of Work): Project involves software system but no embedded product. And the development is based on an existing software platform.

Subgroups: A1 – Embedded product platform project: Project involves embedded product and requires to develop a new embedded platform.
20 People, 2 Basic Units
– A1 – Embedded product platform project

B1 – Software system platform project: Project involves software system but no embedded product. And it requires to develop a new software platform.
23 People, 4 Basic Units
– B1 – Software system platform project

B2 – Software system improvement project: Project involves software system but no embedded product. And the development is based on an existing software platform.
13 People, 2 Basic Units
– B2 – Software system improvement project