| Sampling Factors: |
Location (Not Relevant: There is only one location, which is Hangzhou)
Customer: The customers are categorized as Government and Enterprise
Size (Not Relevant: All projects are medium scale, from 60 staff months to 90 staff months)
Organizational Structure (Not Relevant: Projects in team I & II are part of Software Division, they share same management team)
Type of Work (Not Relevant: All projects are MIS (management information system) related application development) |
| Sampling Factor Values: |
GOV (Customer): The customers are from government
ENT (Customer): The customers are from enterprise |
| Subgroups: |
Team I: The projects are developed for government customers
31 People, 4 Basic Units
– GOV
Team II: The projects are developed for enterprise customers
14 People, 2 Basic Units
– ENT |