| Sampling Factors: |
Location (Not Relevant: The appraisal is focused on One Location – Hangzhou, Zhejiang)
Customer (Not Relevant: All projects are focused on Power Industry)
Size: The projects can be treated as large or small projects
Organizational Structure (Not Relevant: All projects report to Technical Department Head)
Type of Work (Not Relevant: The focus is oonly on full life cycle development activities) |
| Sampling Factor Values: |
Large Projects (Size): Projects with 50 person months or more effort are treated as large projects
Small Projects (Size): Projects with less than 25 person months are treated as small projects |
| Subgroups: |
Large Projects: Projects with 50 person months or more effort are treated as large projects
42 People, 3 Basic Units
– Large Projects
Small Projects: Projects with less than 25 person months are treated as small projects
29 People, 6 Basic Units
– Small Projects |