| Sampling Factors: |
Location (Not Relevant: All projects are performed in the same location: Wuhan.)
Customer (Not Relevant: There are all commercial customers, and follow the same R&D process.)
Size (Not Relevant: The OU follow agile processes, projects development will be divided into fixed iteration cycle and follow the same agile processes, so size is not a sampling factor.)
Organizational Structure: There are two development department, in charge of different system development.
Type of Work (Not Relevant: All projects are SW development projects.) |
| Sampling Factor Values: |
RPL (Organizational Structure): The RD&PO for Production Line Department is responsible for map data production tool/system development.
MPS (Organizational Structure): The Map Perception System Department is responsible for map perception system development. |
| Subgroups: |
1: Map data production tool/system development projects.
58 People, 5 Basic Units
– RPL
2: Map perception system development projects.
78 People, 6 Basic Units
– MPS |