| Sampling Factors: |
Location (Not Relevant: Software is developed in the Hefei office, and therefore location does not influence process selection.)
Customer (Not Relevant: The OSSP processes are developed at organisational level and processes are not different for customers. Software is contracted development for Enterprise consumers.)
Size (Not Relevant: The OSSP processes does not vary differently for different size of the projects.)
Organizational Structure (Not Relevant: There is one major division “Implementation Center” Software products and services are provided by the Implementation Center and therefore the structure does not influence process selection.)
Type of Work: Hefei Theone City Intelligent Technology Co., Ltd. executes Development and Maintenance projects, which are executed using Waterfall development life cycle. Same sets of processes are followed for execution of both type projects. But “TYPE OF WORK” factor is considered for the project selection. |
| Sampling Factor Values: |
Development Project (Type of Work): Project with the development detailed as per value of sampling factor
Maintenance Project (Type of Work): Project with the maintenance detailed as per value of sampling factor |
| Subgroups: |
Development Project: Project with the development detailed as per value of sampling factor
8 People, 2 Basic Units
– Development Project |