- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: No process difference with project locations. One location, Zhengzhou city.) Customer (Not Relevant: The customers of the projects are same, all are enterprises.)
Size (Not Relevant: No difference in practice-implementation as per the size, all projects have a similar size in each subgroup.)
Organizational Structure (Not Relevant: One organization structure. All projects are under the same command chain.)
Type of Work: Practice implementation are different in project types, there are product maintenance projects and product development projects
Sampling Factor Values: PM (Type of Work): The project in this type applies small changes for enhancement and/or fix bugs on an existing system PD (Type of Work): The project in this type develops new system
Subgroups: SUB1: Product Maintenance Project
This subgroup is to apply small changes for enhancement and/or fix bugs on an existing system
15 People, 2 Basic Units
– PMSUB2: Product Development Project
This subgroup is to develop new system
14 People, 2 Basic Units
– PD