| Sampling Factors: |
Location (Not Relevant: All Basic Units within the ORG perfortheir tasking at the Zhengzhou city site. As such, there are not differences in implementation in therms of location. This Sampling Factor iot relevant.)
Customer (Not Relevant: The customers are enterprises f.or the 2 projects. There is no difference based on customer.)
Size (Not Relevant: All projects are between 1 and 2 main-months and have 4 FTEs. The size difference is minimal and does not affect the way the projects implement the processes. This Sampling Factor is not relevant. The duration of the projects are 6 months. The range is not significant in how the projects perform the processes.)
Organizational Structure (Not Relevant: All the basic units fit within the same organizational department, Project Implement Center. Therefore, this sampling factor is not relevant.)
Type of Work: Project 1 is Maintenance project; Project 2 is Development project. Work is performed differently. |
| Sampling Factor Values: |
New Development (Type of Work): To develop a new type of system
Maintenance (Type of Work): To maintain and improve an old verson |
| Subgroups: |
1: To develop a new type of system
6 People, 1 Basic Units
– New Development
2: To maintain and improve an old version
6 People, 1 Basic Units
– Maintenance |