Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: No.All projects are in the same location, so this is not a relevant sampling factor)
Customer (Not Relevant: No.Customers varies, but the work process does not differ. Hypothesis testing of the process performance parameters also indicates that customer is a not a relevant sampling factor)
Size: Hypothesis testing of the process performance parameters indicates that size is a relevant sampling factor
Organizational Structure (Not Relevant: No. All projects are in R&D center, so this is not a relevant sampling factor.)
Type of Work (Not Relevant: No. All projects are in R&D center and similar type, so this is not a relevant sampling factor.)
Sampling Factor Values: Large projects (Size): Size is greater than 380 UCP
Small (Size): Size is less than 380 UCP
Subgroups: Large projects: Size is greater than 380 UCP
21 People, 2 Basic Units
– Large projects
Small Projects: Size is less than 380 UCP
22 People, 4 Basic Units
– Small