| Sampling Factors: |
Location (Not Relevant: The way of their work is not changed by the location, so this is not a relevant sampling factor.)
Customer (Not Relevant: The way their work is not changed by the customer, so this is not a relevant sampling factor)
Size: Projects in this organization are categorized in the sizes based on complexity and effort involved. Project manager and QA group apply a different set of processes for project depending on the size of a project. – Large (Project > 30 People) – Medium & Small (Project <= 30=””>
Organizational Structure (Not Relevant: The way their work is not changed by the organization, so this is not a relevant sampling factor)
Type of Work: Projects in this organization are categorized in the sizes based on complexity and effort involved. Project manager and QA group apply a different set of processes for project depending on the size of a project. |
| Sampling Factor Values: |
Large (Size): Projects in this organization are categorized in the following sizes based on complexity and effort involved (large project > 30 people)
Medium & Small (Size): Projects in this organization are categorized in the following sizes based on complexity and effort involved (Medium/Small project <= 30=””>
New Development (Type of Work): All the new development projects are the first development for the new system(product)
Series Development (Type of Work): All projects of Series development are in the 2nd or more iteration stage after completion of the first development. |
| Subgroups: |
Large-New: The New large-size development projects in the first development stage
70 People, 2 Basic Units
– Large
– New Development
Large-Series: The Large size development projects in the series development stage
68 People, 2 Basic Units
– Large
– Series Development
Medium-New: The New Medium(or Small)-size development projects in the first development stage
52 People, 3 Basic Units
– Medium & Small
– New Development |