| Sampling Factors: |
Location (Not Relevant: The OU has only one location)
Customer (Not Relevant: The OU has only one type of customer: machinery)
Size: The OU has defined three types of project size: Large, Medium and Small
Organizational Structure (Not Relevant: The OU has only one development branch)
Type of Work: The OU has defined two types of projects: New Development and Upgrade |
| Sampling Factor Values: |
Small (Size): Projects with estimated effort of less than 20 person-month
Medium (Size): Projects with estimated effort of 20~100 person-month
Large (Size): Projects with estimated effort of more than 100 person-month
ND (Type of Work): New Development
UG (Type of Work): Upgrade |
| Subgroups: |
SG1: Medium Size New Development Projects
15 People, 2 Basic Units
– Medium
– ND
SG2: Small Size Upgrade Projects
13 People, 2 Basic Units
– ND
– Small |