| Sampling Factors: |
Location (Not Relevant: All of the project teams are located in Nanjing. They develop the similar software and follow the same organizational processes. So the location has no impact on the process implementation.)
Customer: The customer can be divided into two types. One is internal customer and the other is outer customer. The requirement development and design processes are different.
Size (Not Relevant: All of the projects are the similar size, so the project size has no impact on processes implementation.)
Organizational Structure (Not Relevant: There is one core development department in the OU, so the org structure has no impact on processes implementation.)
Type of Work (Not Relevant: They are all software development, so the type of work has no impact on impact on processed implementation.) |
| Sampling Factor Values: |
Internal project (Customer): The customer of internal project is Nanjing steel group.
Outer project (Customer): The customers of outer project are not Nanjing steel group. |
| Subgroups: |
Internal project: All projects are for Nanjing steel group.
38 People, 6 Basic Units
– Internal project
Outer project: The customers of outer project are not Nanjing steel group.
55 People, 7 Basic Units
– Outer project |