| Sampling Factors: |
Location (Not Relevant: OU is in a single location, thus not a potential sampling factor)
Customer: MIS project for end users and Government projects. The government projects have different method of requirements as most of them are done through tenders. They are fixed schedule and fix price. The risks are different than the MIS projects where the price can be extra for change requests and schedule can be negotiated. This primarily impacts following process areas: REQM, RD, PP, PMC, MA, RSKM. Thus this is a potential sampling factor.
Size (Not Relevant: Most of the projects are of similar sized team members and similar sized efforts, thus not a potential sampling factor.)
Organizational Structure (Not Relevant: OU is located in a single location with a singular management structure, thus not a potential sampling factor)
Type of Work (Not Relevant: All basic units are software application development using similar technologies and using the same QMS processes, thus not a potential sampling factor) |