| Sampling Factors: |
Location (Not Relevant: All Basic Units within the Jinpeng Electronic Information Machine Co.Ltd. perform their tasking at the Guangzhou city site. As such, there are not differences in implementation in terms of location.)
Customer (Not Relevant: All projects are self-developed projects, The type of work does not affect the processes used)
Size: Size is based on a man-months (Small, Med, or Large). This affects the process used by the project. For example, according to the tailoring guideline, a large sized project is required to perform a formal review of its feasibility analysis, a medium sized project is allowed to just do a group review and a small sized project is allowed not to do this review.
Organizational Structure (Not Relevant: All the basic units fit within the same organizational department, Research and Development (R&D) Center.)
Type of Work (Not Relevant: All projects are self-developed projects, and the work performed is still conducted per the standard process) |