Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: Org/OU’s main location is Falls Church, VA and processes followed do not differ based on location)
Customer (Not Relevant: Projects are done for the U.S. Defense or Federal Government, not a driver of process variation)
Size (Not Relevant: Project staff size is not a driver for process variances or any major differences)
Organizational Structure (Not Relevant: SOFTWARE SERVICES PROJECTS does not have any further intricacies of complex organization structure or further separation which drives process differences. Hence not relevant.)
Type of Work (Not Relevant: Not relevant since all work is software Services and is the chosen domain.)
All Work: Includes all software development work in SOFTWARE SERVICES PROJECTS. This is included to facilitate the creation of a single sub-group in SAS.
Sampling Factor Values: S1 (All Work): Includes the 3 total projects in SOFTWARE SERVICES PROJECTS
Other (All Work): This is an Empty Set – There are no other projects or work relevant in the OU, created to ensure creation of a single subgroup.
Subgroups: SG1: Includes all the software Services work currently performed in SOFTWARE SERVICES PROJECTS
79 People, 3 Basic Units
– S1