| Sampling Factors: |
Location (Not Relevant: All of the work is performed in a single geographical location (Beijing).)
Customer (Not Relevant: Because all customers are from the global security market, differences in customers do not affect the processes used to perform the work.)
Size (Not Relevant: Comparable project size in terms of team size and duration. This factor does not affect the definition and implementation of development processes)
Organizational Structure (Not Relevant: No influence on the process implementation because of only System Solution Division)
Type of Work: Product R&D projects, Contract projects |
| Sampling Factor Values: |
PRD (Type of Work): Product R&D projects
CP (Type of Work): Contract projects |
| Subgroups: |
SG1: Contract projects
63 People, 8 Basic Units
– CP
SG2: Product R&D projects
42 People, 5 Basic Units
– PRD |