| Sampling Factors: |
Location (Not Relevant: There is only one location so the location does not affect the management of the projects.)
Customer (Not Relevant: Customers do not affect the management of the projects.)
Size: Projects are of short or long duration.
Organizational Structure (Not Relevant: There is only one organizational structure.)
Type of Work (Not Relevant: There is only one type of work.) |
| Sampling Factor Values: |
Long Duration (Size): project period longer than 6 months (project period > 6 months).
Short Duration (Size): project period less than or equal to 6 months (project period <= 6=””> |
| Subgroups: |
R&D_Short Duration Project: project period less than 6 months (project period <= 6=””>
11 People, 2 Basic Units
– Short Duration
R&D_Long Duration Project: project period longer than 6 months (project period > 6 months)
8 People, 1 Basic Units
– Long Duration |