| Sampling Factors: |
Location: OU”s project teams either are all in the same site or multiple sites.
Customer (Not Relevant: Bank of China is the only customer and the customer is not a relevant.)
Size: The size includes two values: large (> 1000 man days)and small (< 1000=”” man=””>
Organizational Structure (Not Relevant: The development departments are organized based on domains and they have no impact on the process used.)
Type of Work (Not Relevant: Only the new development projects or major enhancements are included in the appraisal. The process is the same for them, thus it is not relevant.) |
| Sampling Factor Values: |
Same Site (Location): It covers projects whose teams are located in the same site.
Multiple Sites (Location): It covers projects whose teams are located in different sites.
Large (Size): It covers projects whose total efforts are more than or equal to 1000 man days.
Small (Size): It covers projects whose total efforts are less than 1000 man days. |
| Subgroups: |
Small + SS: The subgroup includes projects whose size are large and all teams are located in the same site.
77 People, 10 Basic Units
– Small
– Same Site
Large + MS: The subgroup includes projects whose size are large and teams are located in different sites.
900 People, 40 Basic Units
– Large
– Multiple Sites
Large + SS: The subgroup includes projects whose size are large and project teams are located in the same site.
198 People, 15 Basic Units
– Large
– Same Site |