CMMI认证

Qingdao Yuanzhi Innovation Technology Service Co., Ltd.-2020-CMMI3

Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: The scope of appraisal is Development Department of Qingdao Yuanzhi located at Qingdao. No other location is considered. Qingdao Yuanzhi QMS processes are established at organizational level for Qingdao Location.
So ‘LOCATION’ factor is not considered for project selection.)

Customer (Not Relevant: Development Department develops applications and software for Mobile and Cloud Services clients. In all the basic units, standard process defined at organization level with minor tailoring is followed. No significant changes observed in the processes followed by these projects for different customers.
So ‘CUSTOMER’ factor is not considered for project selection.)

Size (Not Relevant: Development Department QMS processes does not vary and differentiating for different size of the projects. All projects are of typically similar staff size (05-06 staff) with similar duration. There is no variation in the work performed in these projects due to project team size and hence all projects are required to follow same processes irrespective of project team size.
So ‘SIZE’ factor is not considered for project selection.)

Organizational Structure (Not Relevant: Organizational Structure is same for all the software development projects executed in Development Department hence no significant process variation based on organizational structure.

So ‘ORGANIZATIONAL STRUCTURE’ factor is not considered for the project selection.

Following functions / activities are carried out at organizational Level.
1. EPG
2. Quality Management Department
3. Training)

Type of Work (Not Relevant: Development Department executes software development projects using the Waterfall Life Cycle. Same sets of processes are followed for execution of these projects.
So ‘TYPE OF WORK’ factor is not considered for project selection.)

Life Cycle: All Projects follow Waterfall Life Cycle. Though Life Cycle factor does not have any impact, ‘LIFE CYCLE’ factor is considered for project selection.

Sampling Factor Values: Waterfall Life Cycle (Life Cycle): Projects which follows Waterfall life cycle for project execution

No Life Cycle (Life Cycle): –

Subgroups: Waterfall Life Cycle: Projects which follows Waterfall life cycle for project execution
11 People, 2 Basic Units
– Waterfall Life Cycle

版权所有丨如未注明 , 均为原创丨本网站采用BY-NC-SA协议进行授权
转载请注明原文链接:Qingdao Yuanzhi Innovation Technology Service Co., Ltd.-2020-CMMI3