| Sampling Factors: |
Location (Not Relevant: There is only one location)
Customer (Not Relevant: There is no process distinctions made based on the customers)
Size: The projects are categorized as big (more than 15 staff month) and small (no more than 15 staff months)
Organizational Structure (Not Relevant: There is no process distinctions made based on the organization structure.)
Type of Work (Not Relevant: There is no process distinctions made based on the type of work.) |
| Sampling Factor Values: |
Big (Size): The effort used in this project is more than 15 staff months
Small (Size): The effort used in this project is no more than 15 staff months |
| Subgroups: |
Expressway: Projects developed in this subgroup are applications for expresss way.
13 People, 3 Basic Units
– Big
Equipment apps: Projects developed in this subgroup are equipment applications.
8 People, 2 Basic Units
– Small |