| Sampling Factors: |
Location (Not Relevant: There is only one location for the OU)
Customer (Not Relevant: There are multiple customers; but the process remains the same)
Size (Not Relevant: All projects currently falls under same project category with no change in process)
Organizational Structure (Not Relevant: The OU is small with flat organizational structure. The PMs report to Dept. Manager who in turn reports to the General Manager. There is no impact of org. structure on the process deployed)
Type of Work: There are two types of workstream namely “Product” and “Project” |
| Sampling Factor Values: |
PROD (Type of Work): Product Development
PROJ (Type of Work): Project Work |
| Subgroups: |
Project 1: APEX delivery system
27 People, 1 Basic Units
– PROD
Project 2: The Grain Trading System
39 People, 1 Basic Units
– PROJ |