- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: NOT a relevant sampling factor since the project in scope and the OU in scope are located in Shanghai) Customer (Not Relevant: NOT a relevant sampling factor since the domain of software development is new product development that is industry and customer neutral.)
Size (Not Relevant: NOT a relevant sampling factor since the single project in scope is a small project with 8 members on the team)
Organizational Structure (Not Relevant: NOT a relevant sampling factor since the execution of software activities aligned to the CMMI-DEV V1.3 is in the single subgroup of R&D Center)
Type of Work: ONE out of THREE critical-to-business sponsor selected JAVA project
Sampling Factor Values: Sponsor Selected (Type of Work): ONE out of THREE Java projects which is critical to the sponsor’s business objectives. Sponsor Excluded (Type of Work): TWO out of THREE maintenance and support projects that is NOT critical to addressing the sponsor’s business objectives
Subgroups: R&D Center- Second verification of process approval Project: This single Basic Unit which is in scope addresses a core functionality which is reused by other basic units.
6 People, 1 Basic Units
– Sponsor Selected