| Sampling Factors: |
Location (Not Relevant: All projects located in Chengdu office)
Customer (Not Relevant: All customers are external financial organization.)
Size: Size of Project Based on Estimated Function Point Count
Organizational Structure (Not Relevant: All projects are within the Information Technology Department under the same management structure)
Type of Work (Not Relevant: All projects are software development of systems for external customers. All projects are web developments for financial data.)
Lifecycles: Lifecycle use during software development |
| Sampling Factor Values: |
Small (Size): Project estimated to be less than 50 function points.
Medium (Size): Project estimated between 50 and 100 function points.
Large (Size): Project estimated to be greater than 100 function points.
Waterfall (Lifecycles): Project using waterfall lifecycle
Incremental (Lifecycles): Project using incremental lifecycle |
| Subgroups: |
Waterfall/Medium: Project estimated between 50 to 100 function points using waterfall lifecycle
4 People, 2 Basic Units
– Medium
– Waterfall
Incremental/Large: Project estimated larger than 100 function points using incremental lifecycle
3 People, 1 Basic Units
– Incremental
– Large |