| Sampling Factors: |
Location (Not Relevant: All the SW product development projects only located in one location: Shanghai City, China.)
Customer (Not Relevant: Product Requirement elicitation and version planning is conducted by consolidating needs from different customers. So customer has not significant impact on product development)
Size (Not Relevant: Project teams are divided into small agile teams, so size do not have significant impact on process definition and implementation)
Organizational Structure: There are 2 product lines, OSSWorks product series and IM(Integration Manager) product series. So it is a critical sampling factor
Type of Work (Not Relevant: This appraisal only cover SW product development projects. So it is not a critical sampling factor) |
| Sampling Factor Values: |
OSSWorks product series (Organizational Structure): OSSWorks product series development projects
IM product series (Organizational Structure): IM(Integration Manager) product series SW product development projects |
| Subgroups: |
G1: OSSWorks product series SW product development projects
11 People, 2 Basic Units
– OSSWorks product series
G2: IM product series SW product development projects
15 People, 2 Basic Units
– IM product series |