CMMI认证

Telligen-2013-CMMI3

Sampling Summary:
(抽样汇总)
Sampling Factors: Location (Not Relevant: There is only one location – Des Moines, IA)
Customer (Not Relevant: There are a limited number of customers, and the same processes are used for all.)
Size (Not Relevant: The size of the project does not affect the processes used.)
Organizational Structure (Not Relevant: There is only one organizational unit within the appraisal scope – Information Management)
Type of Work (Not Relevant: The type of work does not affect the way that work is performed)
Lifecycle: In the past, most of the work was performed using a Waterfall life cycle. The organization has since migrated to mostly Scrum-based projects, although 2 legacy products continue to use Waterfall.
Sampling Factor Values: Waterfall (Lifecycle): Traditional Waterfall development, currently only used for 2 legacy products.
Scrum (Lifecycle): Agile development is now being used for most of the projects.
Subgroups: Waterfall Subgroup: Projects using Waterfall life cycle
39 People, 5 Basic Units
– Waterfall
Scrum Subgroup: Projects using agile development methodology.
28 People, 3 Basic Units
– Scrum

版权所有丨如未注明 , 均为原创丨本网站采用BY-NC-SA协议进行授权
转载请注明原文链接:Telligen-2013-CMMI3