- Sampling Summary:
(抽样汇总) -
Sampling Factors: Location (Not Relevant: All projects are executed from one location Tianjin City) Customer: Internal and External Customers
Size (Not Relevant: All projects are approximately of similar size. ?
No difference in process due to size.)Organizational Structure (Not Relevant: there is no difference in process implementation in the BU due to organizational structure)
Type of Work (Not Relevant: All are development projects)
Sampling Factor Values: Internal (Customer): Full development project for Internal customers External (Customer): Customization project for external customers
Subgroups: G1: Internal Customers
16 People, 2 Basic Units
– InternalG2: External customers
20 People, 2 Basic Units
– External