| Sampling Factors: |
Location (Not Relevant: All Basic Units within the WISCOM INFORMATION SYSTEM CO., LTD. perform their tasking at the Nanjing city site. As such, there are not differences in implementation in terms of location. This Sampling Factor is not relevant.)
Customer (Not Relevant: All of the products are provided to external customers. This factor does not drive a difference in process implementation. This sampling factor is not relevant.)
Size (Not Relevant: All projects are similar in size. Project size does not affect the process used. This Sampling Factor is not relevant.)
Organizational Structure (Not Relevant: All the basic units fit within the same organizational department and reporting structure, R&D Center. This does not affect the processes implemented. Therefore, this sampling factor is not relevant.)
Type of Work: There are two types of projects, New-development and Maintenance- development. This factor drives difference in process implementation. This sampling factor is relevant. |
| Sampling Factor Values: |
New-Development (Type of Work): Projects are new and contract-based. They are developed for designated customers.
Maintenance-Development (Type of Work): Projects are to maintain development from original projects |
| Subgroups: |
New Development: Projects are new and contract-based. They are developed for designated customers.
24 People, 4 Basic Units
– New-Development
Maintenance-Development: Projects are to maintain development from original projects
15 People, 2 Basic Units
– Maintenance-Development |