| Sampling Factors: |
Location (Not Relevant: ALL the projects are developed in Wuhan. No effect on CMMI implementation.)
Customer (Not Relevant: The OSSP is applied for all customers. No effect on CMMI implementation.)
Size: when the size of project is more than 50, there are some effects on CMMI implementation.
Organizational Structure (Not Relevant: All projects are developed in the Department of Software Research & Development Department.No effect on CMMI implementation.)
Type of Work (Not Relevant: The type of work is only project development. There are the same processes for the project development. No effect on CMMI implementation.) |
| Sampling Factor Values: |
large (Size): more than 50
small (Size): less than 50 |
| Subgroups: |
Project development: Project development
62 People, 9 Basic Units
– small |