| Sampling Factors: |
Location (Not Relevant: All projects are worked in the same location, so location does not impact process execution.)
Customer (Not Relevant: All projects are developed for electric industry customer, so no impact on process execution.)
Size (Not Relevant: All projects are worked in the same size, so no impact on process execution.)
Organizational Structure (Not Relevant: All projects are worked by the same group, so organizational structure does not impact process execution.)
Type of Work: Projects have different tailoring based on new development projects and upgrading development projects. |
| Sampling Factor Values: |
New development work (Type of Work): New development projects must follow OSP and have little tailoring
Upgrade development work (Type of Work): Upgrading development projects based on former projects and can have more tailoring. |
| Subgroups: |
New Development Projects: New development projects must follow OSP and have little tailoring
14 People, 2 Basic Units
– New development work
Upgrade Development Projects: Upgrading development projects based on former projects and can have more tailoring
22 People, 4 Basic Units
– Upgrade development work |